Support Central will be taking a maintenance break on Sunday 25 February 2018 – 2 hours, between 8pm and 10pm AEST.

You are here

Set the project’s working week

To keep your workflows on track, set the working week for your project.

The timeframes in Workflows operate on the basis of working days. But what are “working days”? The days teams work may differ between projects and locations.

Set the project working week to make sure your workflows stay on track.

  1. Select your project in the Project Selector at the top of the page.
  2. Click the Setup button on the Module Menu, and under Project, click Project Settings.

Selecting project settings
  1. Click the Document Review tab.

  2. Scroll to the Project Working Week section. By default, the days Monday to Friday will be selected, but you can change this if your project teams work other days of the week.
     
  3. Click the checkboxes to select or deselect certain days of the week.
Slecting days of the project working week
  1. Click Save in the top right-hand corner of the page to save your new settings.