You are here

Close out project mail for more accurate reporting

When an activity is complete, close out related project mail so you can monitor active items more easily.

Close out project mail to get accurate project status reports. You can close out any project mail sent by your organization, but typically, you'd close out formal communications such as RFIs.

  1. Select your project from the Project Selector at the top of the page.
Banner Project Selector
  1. Click the Mail button on the Module Menu, and under Search, click Sent.
Sent Menu
  1. Complete one or more search criteria fields.
  2. Click the Search button.
Search Criteria
  1. Click the Subject link to display the project mail you want to close out.
Subject Link
  1. Click the Close Out Mail button.
Mail Button