Submit, close, or reopen a test plan on Mobile

After all activities on a test plan are completed, it needs to be submitted for a final approval and then closure.

After the Manager marks all activities as completed, they can submit the test plan for final approval. Once submitted, the Approver closes the test plan.

Submit a test plan

A Manager (or Approver) can submit a test plan once all activities are marked completed and all inspections within the activities are closed.

  1. To submit a test plan, open the test plan details and tap Submit at the bottom of the screen. 
  2. The status of the test plan will change from In Progress to Submitted.

Mark a test plan as in progress

If you submitted the test plan by mistake, or identified additional work to be done, you can change the status of the test plan back to In Progress

  1. Open the test plan details and tap Update Status at the bottom of the screen. 
  2. Select the In Progress status and provide a reason for moving the test plan back to In Progress.
  3. The status of the test plan will change from Submitted to In Progress.

Close a test plan

An Approver (or Administrator from the Approver's organization) can close a test plan once it's been submitted. 

  1. Review the test plan and activities and ensure they are completed per your requirements.
  2. Tap Update Status at the bottom of the screen. 
  3. Select the Closed status and provide an optional comment.
  4. The status of the test plan will change to Closed.

Nota

If you are not satisfied with the test plan you can mark it as in progress. You must provide a comment.

Reopen a test plan

Sometimes an Approver needs to reopen a test plan. This may be due to additional work identified, human error, changes in the activity requirement, or some updates in the prevailing rules and regulations.

  1. Open the test plan details and tap Reopen at the bottom of the screen. 
  2. You must provide a reason for reopening the test plan. The status of the test plan will change to In Progress.
  3. The Manager can reopen the activity where additional work needs to be performed.