Work Breakdown Structure templates can be assigned to projects when they are created and used as a starting point for baseline development.
Note that while WBS templates can only be applied when you initially enable a project for Cost, you can import a WBS via CSV at anytime.
Control elements are used to categorize types of cost, hours, and quantity data that are budgeted and tracked on a project. Control elements are sub-elements of control accounts, work packages, and progress packages.
To Create a Control Element Category:
Under Cost Administration/Organization Data navigate to Control Element Categories.
Click the Add icon on the toolbar.
Enter a Control Element Category Name.
Select the Category Type.
Click Add Control Element Category.
Changes to Control element categories can also be made by navigating to: