Preventing untracked changes by locking project budgets after it has been set up.
Project budgets are established and approved at the start of a project. These form the basis of the Original Budget in Cost, which is a baseline used for tracking and reporting. Over time, changes to the budget are recorded through the project change process and reflected in the Current Budget.
Budgets should be locked only after the project setup is complete including WBS, control accounts, control elements, schedule activities and time-phased data.
When ready to lock the original budgets
Original budget fields at the Control Element level are now locked and cannot be changed.
When you’re ready to lock the current budget:
The Current Budget and Forecast Fields are now locked and can only be changed using the Budget Changes module.
Note: If using the Alternate Budget fields, you can also stipulate budget changes are used.