Review activities and mark them as completed.
After an assignee marks an activity for review, the reviewers need to complete their reviewer actions (such as a Hold Point). The Manager can then mark the activity as completed.
Once all activities are completed, the test plan can be submitted and closed.
As the Reviewer for an activity you'll need to check the details of the activity and ensure the work has been completed as expected. You can update the review outcome multiple times. Each time you add an outcome, the previous outcome is added to the history of the review action.
As a Manager (or Approver) you can complete an activity that is in review.
Sometimes a Manager (or Approver) needs to update an activity after its been marked as completed. This may be due to additional work identified, human error, changes in the activity requirement, or some updates in the prevailing rules and regulations.